Rooppur set for trial grid connection
Bangladesh’s first nuclear power plant is poised to take two significant steps towards operational readiness, with the Rooppur Nuclear Power Plant (RNPP) expected to connect to the national electricity grid for the first time on a trial basis today (17 November), while an International Atomic Energy Agency (IAEA) expert mission has expressed satisfaction with its emergency preparedness and safety management arrangements.
The initial grid synchronisation, which may allow the plant to supply around 300-400 megawatts (MW) of electricity, will test the national power system’s ability to accommodate nuclear-generated electricity and maintain stable frequency.
At the same time, the IAEA’s assessment of the plant’s emergency preparedness, institutional capacity, management and response mechanisms has provided an important indication of the country’s progress in developing nuclear safety capabilities.
Md Rezaul Karim, chairman of the Bangladesh Power Development Board (BPDB), said he had been informed by the Rooppur project director that preparations were under way to connect the facility to the national grid.
“I have been informed by the project director of Rooppur Nuclear Power Plant that it would be connected to the national grid by tomorrow,” he said.
A Power Grid Bangladesh PLC (PGB) official, however, said several earlier attempts to synchronise the plant with the national grid had failed.
“There is an attempt scheduled, and it is likely to happen. But I cannot say for certain when it will take place.
It will happen very soon,” the official said, requesting that the matter be handled sensitively.According to RNPP authorities, the plant may initially supply around 300-400MW to the national grid. Md Anwar Hossain, secretary of the Ministry of Science and Technology, said grid synchronisation was an essential part of the plant’s testing programme, as it was now technically ready to transfer electricity to the national system.
He explained that the exercise would assess how the national grid responds when electricity generated by the nuclear facility is injected into the system, particularly whether it can maintain a stable frequency.
“Connecting with the power grid is part of a larger test to assess how the national grid behaves when electricity from the nuclear plant is injected into it, particularly whether the system can maintain a stable frequency,” he said.
He said the necessary turbine adjustments had been completed and the next step was to examine the grid’s response to the electricity supply.
“Ultimately, the plant has to be connected with the grid. The adjustments to the turbine have been completed. When it is connected to the grid, we will observe how the grid behaves, what happens to the frequency and whether the system remains stable,” he added.
The plant will remain connected to the grid for a certain period before being shut down for further inspection and observation, which officials described as a routine part of the commissioning process.
“After connecting it, they will observe it for some time and then shut it down again and check. These are normal procedures,” Anwar Hossain said.
He added that the plant could operate for several hours if the initial synchronisation went smoothly and the national grid remained stable. Any technical difficulty, however, would prompt an immediate shutdown.
“If everything works well and the system remains stable, it may run for a few hours. If any challenge arises, it will be shut down immediately. Then it may be connected again,” he said.
An official familiar with the project said several additional tests would be required before the plant could proceed towards commercial electricity generation.
“This is one of the tests. Along with this, around nine more tests will be conducted. If the collaboration works properly, another six tests will follow. After completing all these tests, we will finally move towards commercial electricity generation,” the official said, requesting anonymity.
Describing the upcoming exercise as the first attempt to transfer electricity from the plant to the national grid, Anwar Hossain said the generation-side preparations had been completed.
“Technically, our generation-side work is ready. Now, after generating electricity, we have to evacuate it. This evacuation is what we call grid synchronisation. This is the first time we are attempting it,” he said.
IAEA safety assessment
Meanwhile, an expert delegation from the International Atomic Energy Agency (IAEA) has expressed satisfaction with the emergency preparedness, institutional capacity, management and response mechanisms of the Rooppur Nuclear Power Plant following an on-site assessment under the agency’s Emergency Preparedness Review (EPREV) Mission.
The findings were discussed at a joint meeting held on Monday (16 November) at the conference room of the Ministry of Science and Technology at the Bangladesh Secretariat.
The meeting was attended by Science and Technology Secretary Md Anwar Hossain, Bangladesh Atomic Energy Regulatory Authority Chairman Mahmudul Hasan, Chief Scientific Officer Dr Mahabubur Rahman and Head of the Nuclear Safety Department Dr Md Abdur Rob Sheikh, among other officials.
The IAEA delegation comprised 10 members and was led by expert Mark Breitinger, alongside mission coordinator and IAEA official Adriana-Celestina Baciu.
Bangladesh Atomic Energy Commission Chairman Dr M Moinul Islam, RNPP Construction Project Director Dr Kabir Hossain and Nuclear Attaché at Bangladesh’s Permanent Mission in Vienna Tanvir Hasan also joined the meeting virtually.
Anwar Hossain said the IAEA team had visited the Rooppur facility and examined its emergency preparedness, institutional capabilities, management arrangements and emergency response activities against international standards. Following the inspection, the delegation expressed satisfaction with the measures in place, he added.
Emergency preparedness is a critical component of nuclear power plant safety, particularly in ensuring an effective response to potential incidents. Project officials believe the IAEA review will contribute significantly to evaluating Bangladesh’s capacity for nuclear emergency management, safety oversight and coordinated response.
Project background
Bangladesh’s first nuclear power facility has a total gross generation capacity of 2,400MW through two reactors, each with a gross capacity of 1,200MW. The plant is equipped with Russian Generation III+ VVER-1200 reactor technology.
Construction began with the first concrete pour for Unit 1 on 30 November 2017, followed by Unit 2 on 14 July 2018.
The Bangladesh Atomic Energy Commission owns the project, while Russia’s state nuclear corporation Rosatom is constructing the facility under an initial agreement worth $12.65 billion. Around 90 per cent of the project financing comes from Russian state credit.