Govt plans new rigs, more manpower to strengthen BAPEX
The government has taken a series of initiatives to strengthen the state-owned Bangladesh Petroleum Exploration and Production Company Limited (BAPEX), with a focus on boosting domestic gas exploration and production, enhancing energy security and reducing dependence on imported fuel.
The measures include procuring two new drilling rigs, expanding manpower, conducting 2D and 3D seismic surveys, acquiring modern equipment and preparing a 10-year business plan.
“Measures are being considered to strengthen BAPEX, including equipment procurement, expansion of its organizational structure and exploration of joint venture opportunities,” Petrobangla Chairman Md Abdul Mannan, also a member of the BAPEX Board of Directors.
He said initiatives were also underway to undertake equipment procurement projects, adding that increased exploration and development activities would help raise BAPEX’s own revenue and strengthen its financial capacity.
Under the government’s plan, 150 gas wells will be drilled or worked over by 2031, of which BAPEX has been assigned responsibility for 89.
A proposal to procure a 2,000-horsepower AC-AC VFD-class skid-mounted drilling rig has received final approval at an estimated cost of Tk 577.23 crore, to be financed jointly by the government and BAPEX.
A Development Project Proposal (DPP) has also been prepared to procure another 1,500-horsepower rig at an estimated cost of Tk 647 crore, with financing planned from the Gas Development Fund (GDF) and BAPEX.
BAPEX currently operates five rigs -Bijoy-10, Bijoy-11, Bijoy-12, Bijoy-18 and IPS-1. The two additional rigs will raise the number to seven.
Meanwhile, field-level data collection for 4,500 line kilometres of 2D seismic surveys in Exploration Blocks 7 and 9 has been completed. Of this, 1,960 line kilometres were covered in Block 7 and 2,540 line kilometres in Block 9. Data processing and interpretation are underway and are expected to be completed by April next year, BAPEX sources said.
Under the well-drilling programme, the first phase will continue until January 2028, with BAPEX responsible for drilling and workover operations on 21 of the targeted 50 wells.
Under the second phase, from February 2028 to December 2031, a total of 100 wells will be drilled or worked over. Of these, BAPEX will undertake 68 operations, including drilling 52 new wells and carrying out workovers on 16 existing wells.
According to the company, 10 wells have already been drilled: Tobgi-1, Srikail North-1, Shariatpur-1, Bhola North-2, Ilisha-1, Sundalpur-3, Begumganj-4 West, Jamalpur-1, Srikail-5 and Sundalpur-4. Sundalpur South-1 and Bhola North-3 are currently undergoing testing.
To facilitate the use of gas produced from several fields in Bhola that cannot be supplied to the national grid, work is underway to prepare a DPP for constructing a Bhola-Barishal-Khulna gas pipeline.
BAPEX is also reviewing its manpower and operational capacity. A committee has been formed to expand its organizational structure, with plans to increase its workforce from the existing 1,080 to 1,600 employees.
The company can currently operate three drilling rigs simultaneously using its existing infrastructure and manpower. Plans are being considered to raise this capacity to five rigs, alongside domestic and international training programmes to enhance employees’ technical expertise.
Talking to BSS, BAPEX Managing Director Engineer Md Fazlul Haque said work was underway to procure new rigs and equipment alongside the preparation of a long-term business plan.
The plan, being developed in collaboration with the Institute of Business Administration (IBA) of the University of Dhaka, will set out BAPEX’s exploration, drilling and gas production targets for the next 10 years, he said.
He added that strengthening BAPEX had also been highlighted in the BNP’s election manifesto and that the Prime Minister had held discussions with officials on the necessary steps.
The initiatives are being pursued in coordination with the Planning Commission, the Energy and Mineral Resources Division and Petrobangla.
Meanwhile, BAPEX’s Board of Directors has been reconstituted, with Prime Minister’s Principal Secretary ABM Abdus Sattar appointed as its chairman. Petrobangla Chairman Md Abdul Mannan and senior officials from relevant ministries and departments are among the other board members, while BAPEX Managing Director Engineer Md Fazlul Haque is also a member.
Since the reconstitution, the board has held five meetings between August 22 and October 26.